成人VR视频 has mandated Corenov Constructeurs Inc听to carry out the following project: Wong Building / 20-094 - Space simulator.
Project manager:听Mona Modarressi - mona.modarressi [at] mcgill.ca
Assistant project managers:听Mark Grzywacz - mark.grzywacz [at] mcgill.ca; Thomas Perreault - thomas.perreault [at] mcgill.ca
Construction start:听December 2023
Planned construction end date:听March 2024
Work schedule:听Mondays to Fridays, 6 a.m. to 3 p.m. Any additional hours will be coordinated.
Scope of work:听
The project consists of the renovation of two laboratories (rooms 3062 and 3064) to accommodate the installation of a space simulator. The planned work includes a reorganization of the compressed air system, the installation of electrical outlets, electrical conduits and data wiring conduits, as well as modifications to the HVAC systems.
Impact:
Service shutdowns will be required. Users will be informed in advance.