Upper Main Road

Rendering Upper Main Road

Expected start date:ÌýJune 2024

Expected end date:ÌýOctober 2025

µþ³Ü»å²µ±ð³Ù:Ìý$11,800,000

Following the renovation of the Roddick Gates in 2017 and the upgrade of the lower section of the main road on the downtown campus in 2019, the final step in the redevelopment of ³ÉÈËVRÊÓƵ's main road is set to start in June 2024.Ìý

The project entails the reconstruction of the Upper Main Road, from the Y-intersection up to the area in front of the McCall MacBain Arts Building. The project aims to celebrate Main Road as a pedestrian zone, offering space for congregation, socialization, and events.Ìý

The Y-intersection was redesigned in collaboration with an Indigenous designer and an Indigenous artist. It will pay homage to the diverse Indigenous peoples whose footsteps have marked the land ³ÉÈËVRÊÓƵ is located on.Ìý

As the road gets closer to the mountain, there will be more vegetation and granite compared to the lower main road. The project will also reduce the steep incline of certain parts of the Upper Main Road to improve the area’s accessibility.ÌýÌý

In addition, the project will include new lighting, paving, site furniture, and rainwater management.Ìý

What to expect

¶Ù²¹³Ù±ðÌý

°Â´Ç°ù°ìÌý

Impact Ìý

²Ñ¾±³Ù¾±²µ²¹³Ù¾±´Ç²ÔÌý

June 15th, 2024 – Fall 2025Ìý

  • Demolition of the existing Upper Main Road.ÌýÌý

  • Excavation to allow installation of rainwater management system.ÌýÌý

  • Reconstruction of the Y-intersection and Upper Main Road.Ìý

  • Work in front of Arts Building (west side)Ìý

  • Work in front of Arts Building (east side)Ìý

Ìý

  • Certain parts of the Upper Main Road will be inaccessible to vehicular and pedestrian traffic at times

  • Increased vehicle traffic from the Milton Gates to the mobilization site in front of the Macdonald-Harrington BuildingÌý

  • High levels of noise produced by machinery and equipmentÌý

  • DustÌý

  • Some entrances to surrounding buildings will be closed at timesÌý

  • Alternative routes, including with universal access, will be available and communicatedÌý

  • Work is scheduled to start after Spring 2024 ConvocationÌý

  • During Spring 2025 Convocation, no work that may disturb the event will be allowedÌý

  • Dust reduction measures will be in placeÌý